RFQ Preparation Checklist
- Current 2D drawing and 3D model
- Critical dimensions and acceptance method
- Target material, finish, quantity, and timeline
- Known fit or quality issues from previous suppliers
Manufacturability review for actuator component drawings before prototype or batch machining begins.

| Program Metric | Typical Range | Procurement Value |
|---|---|---|
| DFM clarity | Pre-quote review | Early review prevents avoidable machining, inspection, and assembly problems. |
| Cost-impact features identified | 3–8 per drawing typical | Tight tolerances on non-critical features, deep pockets, and thin walls inflate cost. DFM review flags these for engineering decision. |



Yes. Send the drawing package and mark the dimensions or issues you want reviewed first.
Standard drawings are reviewed within 1–2 business days. Complex assemblies or multi-part packages may take 3–5 days with a detailed clarification list returned.
Inquiry Email
Include drawings, material, finish, tolerances, quantity, and delivery location.